7 Oct 2024
1. ) KEJURUTERAAN ELEKTRIK SRI KRIS SDN BHD 2. ) SRI AYYANAREESWARAR @ SURESH A/L D.KRISHNA DMD MARINE ENGINEERING (M) SDN BHD
- Citation
- JA-12BNCvC-23-09/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- JA-12BNCvC-23-09/2022 (Mahkamah Tinggi)
The appeal was allowed because time for performance was not specified and it was unreasonable to expect completion by February 2019 given TNB approvals and bank guarantee timing; the Sessions Court was wrong to find no work performed and to order full repayment of RM250,000. The unilateral termination was invalid where time was not of the essence, and the proper course is assessment of the defendants' claim on quantum meruit for work done; matter remitted to Sessions Court for assessment; costs to appellants.