5 Oct 2023
PCOM Pacific Sdn Bhd Chu Kok Wei
- Citation
- BA-12BNCvC-8-04/2023 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-12BNCvC-8-04/2023 (Mahkamah Tinggi)
Appellate court affirmed the Sessions Court finding that the Defendant repudiated the BOQ contract and that defects existed, but held Plaintiff failed to prove the quantum of claimed special damages; therefore only nominal damages of RM70,000 are recoverable (with 5% p.a. interest from date of filing). The court reduced the trial costs awarded to Plaintiff from RM30,000 to RM5,450. Defendant's cross-appeal was dismissed.