5 Jul 2024
AH SOON CONSTRUCTION SDN BHD SIMAS-D SDN. BHD.
- Citation
- BA-22C-48-12/2021 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22C-48-12/2021 (Mahkamah Tinggi)
Court dismissed Plaintiff's late payment interest claim because calculations of delayed days and BLR were erroneous or unproved, no written notice under Clause 30.17 was given, and the claim appeared to be an afterthought; court dismissed Plaintiff's challenge to the 21-day delay and the LAD of RM315,000 because the Architect certified 21 days, Plaintiff raised no contemporaneous objection and Defendant was entitled to set off the LAD under the contract; court allowed Plaintiff's claim for the unpaid balance RM295,787.10 for strengthening works because VOs were certified, Defendant failed to…