30 Sept 2021
THRIVE BUILD SDN BHD ANGSANA SETIA SDN BHD
- Citation
- WA-22C-26-03/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22C-26-03/2020 (Mahkamah Tinggi)
Court held Defendant breached the CSA repayment obligation and must pay bank interest as proven (RM89,230.28 after credit for excess payment); claim for final retention RM4,776,139 was premature and struck out for want of audited accounts (liberty to reinstitute); architect's LAD confirmation satisfied clause 4 and contractual LAD payable under the contracts was RM5,740,000 so Defendant must refund the difference RM2,760,000 from the provisional RM8,500,000 deduction; Defendant must pay admitted debt RM44,590.86; judgment entered for Plaintiff RM2,893,821.14 with 5% p.a. interest and costs RM…