27 Sept 2023
1. ) SEMERAK SHIPYARD & MARITIME ENGINEERING SDN BHD 2. ) TRIGSTATION SDN BHD KERAJAAN MALAYSIA
- Citation
- DA-21NCvC-6-05/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- DA-21NCvC-6-05/2020 (Mahkamah Tinggi)
The court held the defendant validly terminated the contracts: defendant complied with contractual procedures (warnings, notice of default, remedial period) and plaintiffs were so behind programme and lacked remedy that termination was justified; plaintiffs failed to prove entitlement to damages; defendant is entitled to recover the main engine, gear box and related equipment paid for by defendant; plaintiffs ordered to surrender equipment and allow defendant access; costs RM30,000 subject to taxation.