3 May 2024
XXXX MASS RAPID TRANSIT CORPORATION SDN BHD
- Citation
- WA-21C-3-05/2016 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-21C-3-05/2016 (Mahkamah Tinggi)
Court concluded on the balance of probabilities that defendant made the representation at the 30.1.2013 meeting and an oral contract was formed on 30.1.2013; defendant breached that contract by pursuing a realignment and failing to take steps to procure the railway scheme approval with the station on plaintiff’s lands; fraudulent misrepresentation was not proven; plaintiff proved reliance losses limited to abortive consultancy fees of RM5,500,000 and is awarded that sum with interest and costs; larger speculative/profit claims were too remote, speculative or inadequately evidenced.