16 Dec 2024
1. ) Khatijah binti Md Ibrahim 2. ) Mansor bin Abdul Manan Northern Skyline SDN BHD
- Citation
- PA-22NCvC-241-12/2019 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- PA-22NCvC-241-12/2019 (Mahkamah Tinggi)
Plaintiffs failed to prove on the balance of probabilities that the SP Order was obtained by fraud or suppression of evidence; the court found a concluded contract existed, P2 acted as P1's authorised representative, the SP Order was not procured by fraud and the impeachment suit is also barred by res judicata in the wider sense; accordingly Plaintiffs' claim to set aside the SP Order is dismissed with costs RM50,000.