14 Mar 2025
Boulevard Pillar Sdn Bhd Goh Hardware & Construction Sdn Bhd
- Citation
- JB-22NCvC-32-11/2023 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- JB-22NCvC-32-11/2023 (Mahkamah Tinggi)
Defendant wrongfully terminated both contracts because, applying the contract payment schedule, no certified progress payments were due at the date of termination; contemporaneous documents (including plaintiff's own confirmation) establish the value of works completed by defendant as at termination; plaintiff proved on balance of probabilities entitlement to damages equal to the additional cost to complete (new contract sums including profit after deducting value of works) and defendant proved unpaid balance for works completed; set-off of counterclaim against plaintiff award ordered.