7 Mar 2013
ASPEC CONSTRUCTION WELLINGTON LIMITED V DELTA DEVELOPMENTS LIMITED HC WN CIV-2012-485-2735
- Citation
- openlaw-d4c3b068_6a01_46ae_b399_331191b45ca0.pdf
- Court
- High Court
The arbitrator's refusal of further extension was reasonable given Delta's repeated failure to comply with the timetable, lack of adequate and timely explanation or evidence of why compliance was impossible, and offers made by the arbitrator to mitigate prejudice; no breach of natural justice occurred and therefore the awards should not be set aside and may be entered as judgment.