15 Jan 2016
MACREADY BUILDING SUPPLIES v PAUL MCCRONE BUILDER LIMITED [2016] NZHC 12
- Citation
- [2016] NZHC 12
- Court
- High Court
The Court granted the interim ex parte order because the caveat would otherwise lapse imminently and the applicant had taken reasonable steps to notify the respondent; preserving the caveat pending further orders was necessary and appropriate, with costs reserved and leave to seek discharge on seven days' notice.