9 Nov 2010
BRENT ADAIR MATHEWS V CD REALTY (PN) LIMITED HC PMN CIV 2010-454-276
- Citation
- openlaw-c038196d_b724_4f52_9b7b_48e65ec0ba61.pdf
- Court
- High Court
Respondent was entitled to costs on a 2B basis but was not entitled to recover costs for commencing a defence or to recover both item 4.10 and item 13 (to avoid double recovery); item 13 is the appropriate allocation for preparation, an item 11 allowance of $200 was warranted for appellant delay in filing the bundle, and the correct total award was $3,208 (not the $8,460 claimed).