KINGSBEER TRANSPORT LTD v MARTIN-BROWER NEW ZEALAND [2021] NZHC 3494
- Citation
- [2021] NZHC 3494
- Court
- High Court
No binding contract was formed on the pleaded essential terms because the parties did not objectively agree on essential elements (notably duration and timing) and no fixed timeframe was committed; accordingly KTL's claims for breach, repudiation, estoppel and misleading/deceptive conduct fail; parts of the restitution/quantum meruit claim were precluded by negotiated settlement of certain invoices and others are reserved for supplementary determination; MBNZ's counterclaims fail.