3 Mar 2010
BODY CORPORATE 172108 V MEADER AND ORS HC AK CIV 2009-404-6868
- Citation
- openlaw-06bc544a_828a_414a_aafc_f04c7d1f21c9.pdf
- Court
- High Court
A s 48 scheme is necessary and expedient: remediation must proceed under a single coordinated programme to protect owners' interests and obtain a code compliance certificate; the Court will approve a framework that requires a single contractor and unified work programme, allows joint project managers (one appointed by Body Corporate and one by MSL) to protect MSL autonomy over Level 12, and requires MSL to meet all costs of Level 12 repairs and contribute to common property remediation (proportion to reflect its unit entitlement, indicated at 11.88%), with the precise scheme to be redrafted a…