20 May 2014
SHELL (PETROLEUM MINING) CO LTD v VECTOR GAS CONTRACTS LTD [2014] NZHC 1072
- Citation
- [2014] NZHC 1072
- Court
- High Court
Vector was entitled to costs of $61,616.00: the court declined blanket Band C for all steps, allowed Band C for preparation of the written submissions (large amount of time reasonably required), allowed Band B for memoranda, appearances and commencement of responses, permitted two sets of submissions because there were two separate substantive appeals, and allowed Band B for the costs appeal; disbursements totalling $2,676.00 were allowed.