13 Jun 2018
GRANDE MEADOW DEVELOPMENTS LTD v CLARK ROAD DEVELOPMENTS LTD NO 2 [2018] NZHC 1394
- Citation
- [2018] NZHC 1394
- Court
- High Court
The application for interim measures was declined because the applicants failed to establish that the harm they alleged was not adequately reparable by an award of damages and failed to show the harm to them would substantially outweigh the harm to the respondent; the applicants' evidence of financial risk was speculative, the practical harm was not quantified, and granting the order risked increasing the respondent's financial exposure and delay.