17 Jul 2008
TOTAL IT LIMITED V DULCIUS DEVELOPMENTS LTD HC CHCH CIV 2008 409 830
- Citation
- openlaw-7e2ae6cf_85c8_43eb_8509_26b14c5802e1.pdf
- Court
- High Court
The Court found there was no credible, substantial dispute over the debt; the retention fund paid to the solicitor did not discharge Total's obligation because Total prevented release of the funds after the retention period expired and did not raise justified claims within that period; therefore the statutory demand could not be set aside.