21 Jun 2019
OCEANIA FOOTBALL CONFEDERATION INCORPORATED v ENGINEERED SOLUTIONS & SYSTEMS LTD [2019] NZHC 1439
- Citation
- [2019] NZHC 1439
- Court
- High Court
Payment claim for instalment 3 (invoice dated 28 Feb 2018 reissued as payment claim) and the hold-daywork claim for relocation (payment claim 3) met s 20 CCA requirements given the lump-sum instalment mechanism in the contract and prior conduct (instalment 2 paid); payment claims for unpriced variations and generalized hold overheads (payment claims 2,4-6) lacked sufficient detail to comply with s 20(2)(e) and therefore were not enforceable by statutory demand. OFC failed to establish a genuine and substantial dispute under s 290(4)(a) or compelling 'other grounds' under s 290(4)(c) to set as…