29 Aug 2013
H & H CONTRACTORS LTD v LEIGHTON CONTRACTORS LTD & Or [2013] NZHC 2225
- Citation
- [2013] NZHC 2225
- Court
- High Court
Clause 45 required H & H to serve a prescribed notice within 15 working days from when it was reasonably aware of the matter (triggered by LW's 28 January 2009 email); H & H failed to comply and did not plead or support estoppel or fraud adequately; clause 45 therefore barred H & H's contractual claims and its FTA claim; all claims against Leighton Works were struck out.