2 May 2018
NORTH EASTERN INVESTMENTS LIMITED v AUCKLAND COUNCIL [2018] NZHC 916
- Citation
- [2018] NZHC 916
- Court
- High Court
Summons for the planner's report was not invalid in substance and, even if technically defective, the report was properly before the Panel; reliance on that material was not unfair given parties' responsibilities to monitor materials and the Panel's procedures; the Panel's zoning and precinct recommendations were rational and supported by evidence and proper consideration; the Council was not required to reconsider post-Panel Environment Court decisions when adopting recommendations; and transferring the MCI from a non-statutory to a control layer was within scope and supported by the plan co…