Vijay Construction (Pty) Ltd v Eastern European Engineering Limited (CC 17 of 2016)
Vijay Construction (Pty) Ltd v Eastern European Engineering Limited (CC 17 of 2016) [2024] SCSC 119 (26 July 2024)
The Plaintiff's claim for rent and damages is dismissed because the period September 2012 to May 2014 was already compensated by the arbitral award, and for the period after May 2014, the Plaintiff failed to prove the temporary buildings were reusable or that it suffered actual loss from not being able to use them elsewhere. The Plaintiff's pleadings did not adequately set out the material facts for a claim based on loss of use, and the evidence presented was insufficient to establish the claim on a balance of probabilities.
Source excerpt
- Jurisdiction
- Res judicata
- Damages
- Pleadings
- Arbitration agreement
- Ownership of temporary buildings