The 1st defendant fundamentally breached the construction contract by failing to complete the works and address the plaintiff's complaints. The plaintiff lawfully terminated the contract under clause 18, but also contributed to the breach by making payments without joint measurement and failing to invoke liquidated damages under clause 13. The 2nd defendant is not liable under the bonds because the plaintiff failed to notify the insurer of the 1st defendant's default prior to termination, as required by the bond terms. Both the main suit and the counterclaim are dismissed due to mutual breach…
Source excerpt
- Breach of contract
- Performance bonds
- Advance payment bonds
- Termination of contract
- Damages
- Counterclaim