23 Sept 2020
GREATER HERO LTD v. FORCE WAY ENGINEERING LTD
- Citation
- [2020] HKCFI 2459
- Court
- Court of First Instance
- Case number
- HCA1152/2020
The summons was warranted; the Defendant had no arguable or cogent defence to remain on the Site; disputes over payment did not justify withholding possession; accordingly the Plaintiff was entitled to possession and to costs incurred in bringing the interlocutory application and attending the hearing, summarily assessed at HK$150,000.