9 Dec 2019
SUNTERLY LTD v. THE INCORPORATED OWNERS OF FAR EAST MANSION
- Citation
- [2019] HKCFI 2917
- Court
- Court of First Instance
- Case number
- HCA1049/2019
Although there were serious questions to be tried, the injunction sought would not prevent the complained-of obstruction because the escalator was already installed and halting works would preserve the obstruction; photos and contractor evidence showed works near completion and the balance of convenience favoured completion rather than stopping works; Sunterly had delayed and the relief sought was therefore ineffective — interlocutory injunction refused and costs awarded to the IO.