17 Apr 2002
WO HING ENGINEERING LTD. v. TYCO ENGINEERING & CONSTRUCTION (HONG KONG) LTD.
- Citation
- WO HING ENGINEERING LTD. v. TYCO ENGINEERING & CONSTRUCTION (HONG KONG) LTD.
- Court
- Court of Appeal
- Case number
- CACV1120/2000
Because the Defendant had abandoned its challenge to the $717,688 component, the court upheld that component of the judgment together with interest at prime rate plus 1% from 24 April 1999 until full payment and held that the successful Respondent is entitled to the costs of the court below.