30 Sept 2016
ETERNITY CONTRACTING & ENGINEERING CO LTD v. CHUNG TAI ROLLER SHUTTERS CO LTD
- Citation
- ETERNITY CONTRACTING & ENGINEERING CO LTD v. CHUNG TAI ROLLER SHUTTERS CO LTD
- Court
- District Court
- Case number
- DCCJ716/2010
The GC Master Programme annexed to the purchase order was incorporated into the Contract fixing completion on 11 July 2008; there was no binding oral collateral agreement giving defendant 17–18 days; defendant alone caused the delay; plaintiff proved loss caused by that delay and is awarded damages after set off totaling HKD186,620.14 plus interest.