1 Feb 2008
SAN FAI CONSTRUCTION & DECORATION ENGINEERING LTD v. TSANG, FUSON
- Citation
- SAN FAI CONSTRUCTION & DECORATION ENGINEERING LTD v. TSANG, FUSON
- Court
- District Court
- Case number
- DCCJ3133/2004
Contemporaneous correspondence and conduct established that San Fai had substantially completed the works by early 2003 and the maintenance/payment period commenced then; Tsang failed to prove the alleged defects or their causation and therefore could not withhold payment or succeed in counterclaim; plaintiff entitled to the unpaid balance with interest and costs.