21 Jun 2013
KIM HUNG CONSTRUCTION & ENGINEERING CO. LTD v. STANDARD REFRIGERATION & ENGINEERING CO. LTD
- Citation
- KIM HUNG CONSTRUCTION & ENGINEERING CO. LTD v. STANDARD REFRIGERATION & ENGINEERING CO. LTD
- Court
- Court of First Instance
- Case number
- HCCT37/2012
The judge held the Arbitrator erred in construing SP 6.02 and SCC 11(4); SP 6.02's tentative possession dates allocate the risk of timing to the Main Contractor and SCC 11(4) only gives entitlement after Architect notification and certification; accordingly leave to appeal was granted and the Interim Award on the Delay Claim was set aside; on the Payment Issue the judge found the contractual scheme (SFDSC 15 and related provisions) meant payment for the delay claim had not yet fallen due and the parties agreed a pay-when-paid arrangement for such claims.