17 Aug 2007
WONG CHUK KIN t/a KIN KEE ALUMINIUM CO v. MILLENNIUM ENGINEERING LTD
- Citation
- WONG CHUK KIN t/a KIN KEE ALUMINIUM CO v. MILLENNIUM ENGINEERING LTD
- Court
- Court of First Instance
- Case number
- HCA876/2004
On construction of the contract documents the monthly progress certifications were provisional and subject to final assessment (within the contractually envisaged finalisation period); estoppel was not established; applying the burden of proof and contemporaneous documentation the court made specific quantum adjustments and awarded the Plaintiff a net judgment after set‑offs and payments, and dismissed the Defendant's contra charge for gondola hire as not arising from the subcontractor's obligation.