17 Sept 2015
FAMTECK ENGINEERING LTD v. YEUNG HIU CHONG t/a FINETEC METAL WORKS
- Citation
- FAMTECK ENGINEERING LTD v. YEUNG HIU CHONG t/a FINETEC METAL WORKS
- Court
- District Court
- Case number
- DCCJ577/2013
Court found a binding partly oral/partly written Agreement made in September 2008 (the unsigned Sub-Sub-Contract was not binding), that the defendant breached by failing to deliver components and complete installation per the plaintiff/Gammon schedule and lacked funds to finish the works, that the delay and inability to perform were serious and justified the plaintiff's termination; accordingly judgment on liability was entered for the plaintiff and the defendant's counterclaim was dismissed.