27 Jun 2018
AFFLUENT CONSTRUCTION CO LTD t/a PO LAM CONSTRUCTION ENGINEERING CO v. YU CHEUNG YIN
- Citation
- [2018] HKCFI 1452
- Court
- Court of First Instance
- Case number
- HCA329/2016
The court found the authentic executed Chinese contract did not contain a liquidated damages clause; the defendant (through his agents/representatives) was responsible for the principal causes of delay (failure to deliver site, failure to amend/submit approved plans and failure to pay AP fees) which under the prevention principle set time at large; additional works were ordered or accepted and costs were payable; accordingly judgment entered for plaintiff for outstanding sums and additional works and the defendant's counterclaim for delay was dismissed.