11 Dec 2007
MISSION & ASSOCIATES LTD v. CHU YIN SANG KEN
- Citation
- MISSION & ASSOCIATES LTD v. CHU YIN SANG KEN
- Court
- District Court
- Case number
- DCCJ1502/2006
The contract was a measured/bill of quantities contract, the Defendant ordered or consented to the additional works recorded in project meeting minutes and is therefore liable to pay the invoice of $292,231.20 for extra works; the Defendant's counterclaim for delay and repair was not proved and is dismissed.