16 Nov 2004
FALCON CONSTRUCTION ENGINEERING LTD v. KIRIN CIVIL ENGINEERING CONTRACTORS LTD
- Citation
- FALCON CONSTRUCTION ENGINEERING LTD v. KIRIN CIVIL ENGINEERING CONTRACTORS LTD
- Court
- Court of First Instance
- Case number
- HCCT11/2003
Falcon contracted to install H‑piles within a 75 mm tolerance and was liable when deviations were established; Kirin proved deviation and recoverable losses limited to direct and foreseeable costs (Maunsell design fee and assessed additional building costs) totalling HKD 760,000; Falcon was not liable for alleged delay because completion was within a reasonable time.