7 Feb 2014
CHAN SHUN KEI t/a CHAN SHUN KEI CONSTRUCTION WORKS v. HONG KONG CONSTRUCTION (HONG KONG) LTD
- Citation
- CHAN SHUN KEI t/a CHAN SHUN KEI CONSTRUCTION WORKS v. HONG KONG CONSTRUCTION (HONG KONG) LTD
- Court
- Court of First Instance
- Case number
- HCCT2/2011
An oral contract was found to exist from June/July 2001 incorporating the terms of SC/041 (including obligations to proceed with due diligence and to pay wages) with the 3.95% management fee deduction forming part of the arrangement; no broad February 2002 daywork agreement was proved (only specific daywork orders were paid), a location‑specific March 2002 WA1 daywork agreement was proved, the Blue & Yellow drawings were excluded as unreliable in favour of the contemporaneous 2003 final account, termination was substantively justified for repudiatory breaches (insufficient resources and unpai…