6 Mar 2009
AU YEUNG LUN KAN v. CHO & PARTNERS ENGINEERING LTD
- Citation
- AU YEUNG LUN KAN v. CHO & PARTNERS ENGINEERING LTD
- Court
- District Court
- Case number
- DCCJ4297/2005
Interim certifications and repeated payments on the basis of the Plaintiff's quotations constituted acceptance by conduct of the measurement basis and rates; undisclosed terms of the Defendant's contract with the main contractor could not be incorporated into the sub-contracts; the Lai King Hospital oral contract was not back-to-back; accordingly Plaintiff was entitled to the claimed outstanding sums and Defendant's counterclaim failed.