9 Oct 2018
P v. M
- Citation
- [2018] HKCFI 2280
- Court
- Court of First Instance
- Case number
- HCCT30/2018
The court held that the tribunal committed a serious irregularity by deciding entitlement on the basis that the September Letter and November Breakdown constituted contractual notice when M had not pleaded or relied on those documents, thereby depriving P of a fair opportunity to address the adequacy of those purported notices; accordingly the court declared parts of the Award to be of no effect pending reconsideration and remitted the issue to the tribunal for directions and further submissions.