GOLDEN WAY ENGINEERING DEVELOPMENT LTD v. GWP ENGINEERING LTD
- Citation
- [2024] HKDC 32
- Court
- District Court
- Case number
- DCCJ2595/2022
Defendant established a cogent and plainly arguable case that the Document dated 3 September 2021, read with the Works Order Summary and the parties' subsequent conduct (including plaintiff obtaining and relying on a Performance Bond referencing that contract), constituted a binding agreement containing Clause 25 which required disputes to be arbitrated. The mediation wording did not impose an absolute pre-condition to arbitration. Accordingly, under s20 Arbitration Ordinance the action is stayed and the parties are referred to arbitration; costs awarded to defendant.