30 Oct 2015
KAR MING ENGINEERING CO LTD v. PACIFIC MARBLE & GRANITE (HK) LTD
- Citation
- KAR MING ENGINEERING CO LTD v. PACIFIC MARBLE & GRANITE (HK) LTD
- Court
- District Court
- Case number
- DCCJ418/2013
On balance of probabilities the plaintiff proved the Original Works claim net of payments but failed to prove the full claimed variation sum due to lack of contemporaneous records and agreement; only HKD60,750 of variation works was established as payable. The defendant failed to prove defective workmanship causally attributable to the plaintiff or the quantum of remedial costs; the counterclaim was dismissed.