MO CONNIE v. LAM KIT YING t/a ONEM IDE CO formerly known as IMM DESIGN WORKSHOP
- Citation
- [2021] HKDC 1535
- Court
- District Court
- Case number
- DCCJ5744/2017
Defendant breached the renovation contracts by failing to complete the works within the contractual period and by delivering substandard workmanship; plaintiff validly accepted the repudiatory breach and terminated the contracts; damages are assessed by reference to expert valuation and actual costs of completion and rectification, and defendant cannot rely on guarantee clauses without completing work.