WINFULL DEVELOPMENT LTD. and Others v. LOBLEY CO. LTD. and Another
- Citation
- WINFULL DEVELOPMENT LTD. and Others v. LOBLEY CO. LTD. and Another
- Court
- Court of Appeal
- Case number
- CACV82/1996
The court held that the tender process created unilateral contractual obligations to accept the highest conforming bids; the highest conforming bids were those made by the 3rd plaintiff's nominee companies; certified cheques payable to solicitors did not satisfy the explicit cashier's‑order requirement; therefore the defendants breached their contractual obligation and the award of damages to Mr. Tsang (3rd plaintiff) was upheld but the judgment was varied to award damages to Mr. Tsang alone.