26 Jan 2024
嘉威大厦(渣華道)業主立案法團 v. 張振傑 AND ANOTHER
- Citation
- [2024] HKLdT 9
- Court
- Lands Tribunal
- Case number
- LDBM82/2019
On the evidence the Tribunal found the June–July 2020 correspondence established an agreement between Applicant (via consultant PWL) and Man Yuen to carry out the outstanding and external wall works (a New Contract) but declined to substitute or quantify Man Yuen’s entitlement absent Man Yuen’s participation and proper valuation; non‑compliance with s20A BMO does not render that New Contract automatically void and the court will not declare it voidable without allowing affected contracting party and owners to be heard; R1 was not responsible for the delay to completion but R1 must indemnify A…