13 Apr 2023
TEWARA SDN BHD LEE CHOON SENG & SONS SDN BHD
- Citation
- JA-12BNCvC-7-04/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- JA-12BNCvC-7-04/2022 (Mahkamah Tinggi)
On the evidence the Plaintiff failed to prove entitlement to claimed progress payments and most of the retention sums because claims were provisional and required final remeasurement/certification and Plaintiff failed to call the project managers; Defendant proved defects, failure to hand over and incurred rectification and delay costs; however documents established a reduced computable retention sum of RM136,926.15 which must be returned to Plaintiff; SCJ's invocation of s114(g) against Plaintiff was erroneous but that error did not alter outcome on the counterclaim.