16 Feb 2024
CMH CONSTRUCTION & BLASTING SDN BHD SRI MATRIX CONSTRUCTION SDN BHD
- Citation
- WA-A72C-3-02/2022 (Mahkamah Majistret)
- Court
- Magistrates' Court
- Case number
- WA-A72C-3-02/2022 (Mahkamah Majistret)
Court found CMGD dated 29.6.2020 triggered the 12-month DLP, notices issued within DLP, defendant agreed then failed/refused to carry out rectification and did not prove prevention by plaintiff; under Clauses 28 and 33 plaintiff validly appointed third parties and backcharged proven costs of RM27,161.40 and RM22,550.00; provisional quantities give way to final re-measurement under Clause 9 so milling final quantum for Additional Right Turn is RM6,530.00; Kampung Sungai Buah final re-measurement yields RM2,929.50 and plaintiff may backcharge RM1,500; plaintiff entitled to equitable set-off of…