21 Apr 2025
GRAND DYNAMIC BUILDERS SDN. BHD. DAMAI CITY SDN. BHD.
- Citation
- WA-24C-143-09/2024 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-24C-143-09/2024 (Mahkamah Tinggi)
The court held the adjudication decision was valid despite being delivered after 45 working days because DCSB caused lawful suspension of proceedings via restraining orders and judicial management filings under Companies Act ss 368 and 410 which tolled the adjudication timeline and prevented continuation without court leave; the adjudicator acted within statutory powers (including rejecting a rejoinder) and properly dealt with issues including Interim Certificate No.24, hence there were no special circumstances or clear errors to set aside or stay the adjudication decision.