15 Oct 2021
TAN CHING CHING EKOVEST CAPITAL SDN BHD
- Citation
- WA-12ANCVC-154-05/2021 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-12ANCVC-154-05/2021 (Mahkamah Tinggi)
The SPA, being a statutory Schedule H contract, cannot validly reflect a 48-month completion period because Regulation 11(3) is ultra vires; therefore the 36-month completion period in Schedule H applies, LAD is calculated from the booking fee date and the purchaser's right accrued on deemed delivery of vacant possession (16.5.2019), the defendant raised no triable issues, and summary judgment for the plaintiff in the sum RM155,302.67 with interest and costs was proper.