26 Jul 2024
LATEX FORM SDN BHD IVORY GLOVE SDN BHD
- Citation
- BA-22NCvC-520-12/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22NCvC-520-12/2022 (Mahkamah Tinggi)
On the balance of probabilities the court found the contract required concurrent installation and that Plaintiff had substantially performed (approx. 95%, 70%, 60%), Defendant breached the payment schedule causing suspension; Plaintiff entitled to payment of RM4,040,000 for completion of machine one and must complete, Defendant's counterclaims for liquidated damages, loss of profit and storage were not proven and are dismissed; Plaintiff awarded interest at 5% p.a. on RM4,040,000 from filing date and costs RM15,000.