26 Feb 2026
GLOBAL FIBER TRENCHERS SDN. BHD. EMNES METAL SDN BHD
- Citation
- WA-A52C-27-05/2025 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- WA-A52C-27-05/2025 (Mahkamah Sesyen)
Plaintiff established a prima facie case by contemporaneous documents and proof of part payment; defendant failed to raise any credible triable issues because the third‑party approval defence is barred by privity, illegality is dislodged by defendant's own instruction to commence work and restitution under Section 66 applies, and partial payment estops defendant from denying liability; therefore summary judgment is appropriate for the unpaid balance of RM129,026.00 plus interest and costs.