19 Aug 2021
TWIN PAVILION DEVELOPMENT SDN BHD LEE ZHENG HAN
- Citation
- WA-12ANCVC-8-01/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-12ANCVC-8-01/2020 (Mahkamah Tinggi)
The appeal is dismissed because the appellant failed to show improper service or a meritorious defence; late payment did not preclude the plaintiff's claim for late delivery damages; the alleged events did not amount to force majeure or frustration of the contract; and delivery is determined by the CFO date, making the default judgment valid and not to be set aside.