14 Mar 2023
Rizal Bina 1. ) Ketua Pengarah Kerja Raya Malaysia 2. ) Jabatan Kerja Raya Malaysia 3. ) Kerajaan Malaysia
- Citation
- AA-21NCvC-5-03/2018 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- AA-21NCvC-5-03/2018 (Mahkamah Tinggi)
The termination was valid because the plaintiff committed a fundamental breach by failing to proceed regularly and diligently as required by Clause 51.1(a)(iii); the NUTPKs complied with contractual requirements and the termination notice of 24/7/2015 was effective. Defendants were entitled to recover completion costs subject to deductions for sums due to the plaintiff; after contractual set-offs and adjustments (including deduction of bank guarantee and disallowance of GST and certain tender supervision costs), the net payable by defendants to plaintiff was RM270,017.65. Plaintiff's substant…