CHEONG CHOY KERUING TEKNIK SDN BHD
- Citation
- DI-B52NCvC-2-07/2023 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- DI-B52NCvC-2-07/2023 (Mahkamah Sesyen)
Because defendant issued work orders and Certificates of Contractor Completion (CCC) and processed payments for January–May 2022, it was estopped from treating those payments as 'advance payments' to justify withholding sums for June–September 2022; on the balance of probabilities the court accepted plaintiff's evidence and allowed plaintiff's claim in the quantified amounts, while permitting limited allowed deductions (diesel) and rejecting defendant's counterclaim.