HATIMUDA SDN BHD 1. ) Kerajaan Negeri Sembilan 2. ) SETIAUSAHA KERAJAAN NEGERI SEMBILAN 3. ) SYARIKAT AIR NEGERI SEMBILAN SDN BHD
- Citation
- NA-21C-1-12/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- NA-21C-1-12/2020 (Mahkamah Tinggi)
Plaintiff's claims failed because the contracts were Design and Build fixed price contracts which barred additional quantity and provisional-sum claims absent written approval by the Project Director, which approval was not obtained; accordingly defendants were not liable and the claim was dismissed.